Knooppunt Oost (demo)
Agreements
Read from the BIM execution plan and confirmed by the project team.
Read from the BIM execution plan and confirmed by the project team. Every agreement shows the page it came from.
Documents
| Title | Date | |
|---|---|---|
| BIM execution plan v3 | 2026-06-12 | Download |
Open questions
- Section 4.3 mentions both OpenRoads 2023 and 2024 for the client's engineer. Which one is leading?
Software and versions
| App | Version | Used for | Source |
|---|---|---|---|
| Revit | 2025 | structures | BIM execution plan v3 · p. 14 · §4.2 Software |
| Civil 3D | 2025 | roads and drainage | BIM execution plan v3 · p. 14 · §4.2 Software |
| OpenRoads Designer | 2023 | alignment design by the client's engineer | BIM execution plan v3 · p. 15 · §4.3 Client software |
CDE and status codes
ACC · S0 Work in progress · S1 Shared for coordination · S3 For review · A1 Accepted
Source: BIM execution plan v3 · p. 18 · §5.1 CDE
Naming
KNO-<originator>-<zone>-<level>-<type>-<role>-<number>
Source: BIM execution plan v3 · p. 21 · §6.1 Naming
Coordinates
RD New (EPSG:28992) · NAP
Source: BIM execution plan v3 · p. 23 · §6.4 Coordinates
Exchange formats
IFC 4.3 · BCF 3.0
Source: BIM execution plan v3 · p. 24 · §7 Exchange
Classification
NL-SfB · OTL (IMBOR)
Source: BIM execution plan v3 · p. 26 · §8 Classification
Milestones
| Milestone | Date | Source |
|---|---|---|
| DO-freeze | 2027-03-01 | BIM execution plan v3 · p. 33 · §10 Milestones |
| Permit application | 2027-04-15 | BIM execution plan v3 · p. 33 · §10 Milestones |
| UO delivery | 2027-09-01 | BIM execution plan v3 · p. 33 · §10 Milestones |