Knooppunt Oost (demo)
This week
2026-09-20 – 2026-09-26
What the teams did
Ruben Smit · 2026-09-25
A private session (not shared).
Eva Kok · 2026-09-25
- Fixed the wall types in the structural model after the handoff from the BIM coordinator; delivery check passes for walls.
Daan Mulder · 2026-09-25
- Imported the Relatics export of 25 September: 12 requirements still lack a verification method, 3 fewer than last week.
- Risk review: the late MEP input is now linked to the DO-freeze milestone; mitigation owner proposed.
- Sent the updated clash report to the client.
Sanne Visser · 2026-09-24
- Processed the coordination session of 22 September: 3 decisions, 5 tasks for 4 people, 1 handoff to modeller-structure.
- Triaged 47 open ACC issues; 9 overdue, clustered into 3 groups around the east abutment.
Due in the next 14 days
| Task | Name | Position | Due |
|---|---|---|---|
| Propose a mitigation owner for the late MEP input risk | Daan Mulder | design-coordinator | 2026-10-02 |
| Follow up with Tom Hendriks on the revised drainage routing | Sanne Visser | bim-coordinator | 2026-10-03 |
| Check the abutment clash with the drainage pipes | Ruben Smit | modeller-structure | 2026-10-06 |
Recent decisions
| Date | Decisions |
|---|---|
| 2026-09-23 | Zones C and D added to the file naming convention |
| 2026-09-22 | Deck slab thickness 450 mm |