2026-09-20 – 2026-09-26

What the teams did

Ruben Smit · 2026-09-25

A private session (not shared).

Eva Kok · 2026-09-25

  • Fixed the wall types in the structural model after the handoff from the BIM coordinator; delivery check passes for walls.

Daan Mulder · 2026-09-25

  • Imported the Relatics export of 25 September: 12 requirements still lack a verification method, 3 fewer than last week.
  • Risk review: the late MEP input is now linked to the DO-freeze milestone; mitigation owner proposed.
  • Sent the updated clash report to the client.

Sanne Visser · 2026-09-24

  • Processed the coordination session of 22 September: 3 decisions, 5 tasks for 4 people, 1 handoff to modeller-structure.
  • Triaged 47 open ACC issues; 9 overdue, clustered into 3 groups around the east abutment.

Due in the next 14 days

TaskNamePositionDue
Propose a mitigation owner for the late MEP input riskDaan Mulderdesign-coordinator2026-10-02
Follow up with Tom Hendriks on the revised drainage routingSanne Visserbim-coordinator2026-10-03
Check the abutment clash with the drainage pipesRuben Smitmodeller-structure2026-10-06

Recent decisions

DateDecisions
2026-09-23Zones C and D added to the file naming convention
2026-09-22Deck slab thickness 450 mm