Coordination session · 2026-09-22

coordination

Processed by Sanne Visser · Participants: Sanne Visser, Daan Mulder, Eva Kok, Ruben Smit, Mila Peters, Tom Hendriks

Summary

  • Twelve new clashes since the last session, mostly structure versus drainage near the east abutment. [00:00:03]
  • The deck slab over the new slip road needs to be thicker; decided at 450 mm. [00:31:05]
  • MEP input for the pumping station is late again and could affect the DO-freeze. [00:25:40]

Decisions

#DecisionReplacesAt
i-03Deck slab thickness 450 mm2026-09-01-deck-slab-40000:31:05

Actions

ActionWhoPositionDueAt
Check the abutment clash with the drainage pipesRuben Smitmodeller-structure2026-10-0600:14:32
Fix the wall types in the structural modelmodeller-structure (position)modeller-structure2026-10-0100:20:10
Send the updated clash report to the clientDaan Mulderdesign-coordinator2026-09-2600:55:30

External actions

  • Tom Hendriks (MEP): deliver revised drainage routing (due 2026-10-03) [00:15:02]

Risks and issues raised

  • Late MEP input could delay the DO-freeze. [00:25:40]

Proposed rule changes (waiting for approval)

  • Add zones C and D to the file naming convention (approved 2026-09-23). [00:47:50]